Natural Gas Line Upgrade Progress Update
As of July 18, 2025: Main Line – 91% Complete. Service Line – 67% Complete. Main line crews have a small portion to finish up in the Bradley Street area — about 1,000 ft of main line. In total, it should take from a week to two weeks to install this portion of main line […]